Electrical contractors employed by BEAR Scotland have installed a trial section of seawall lighting that has been well received. The remainder of the wall will…
Largely the road widening and promenade project is complete. Just a few minor snags on Shore Street require attention together with the installation of some…
We are pleased to report that the disruptive works are all but complete. The roads, pavements and cycleway have been resurfaced and fresh road markings…
The project area has progressed well and the main areas of pavement, roadway, cycleway and quayside have been re-surfaced with base coat tar. The top…
The project continues to progress well with all elements starting to take shape. In the coming days the new quayside area at the harbour, the…
All good on the project front with excellent progress across the works. Dredging to deepen the new inner harbour and approaches plus deepening of all…
Shore Street Project Update Work continues on all fronts; the beach steps were installed last week and the two beach ramps are progressing well, the…
Work continues apace. The main elements of the work which have been ongoing over the past month include rainwater drainage, road crossings, concrete seawall shuttering…
Following the two-week Christmas holiday closure the contractor has returned to continue the promenade works and make a start on the Shore Street drainage system.…
Shore Street Project Update The works have progressed well in the past few weeks. Piling is now complete, long reach digger dredging and rock armour…