The project is going well; the contractor worked a couple of Saturdays to make up for lost time due to strong winds. The piling is now around 60% complete and the remaining sheet-piles and tubes will be driven as a priority. The rock armour revetment is slowly taking shape; the machine drivers are taking time to place each piece of stone carefully to achieve a tidy finish. Weekly project updates are displayed on the harbour website along with the first four weeks timelapse video produced by Steven Gourlay. If you have any issues or questions please do not hesitate to get in touch – info@ullapool-harbour.co.uk or 01854 612724.